Google “Project Cannoli” Data Center — Van Buren Township
Approved as of November 15, 2026[20] Van Buren Township, Wayne County
Panattoni Development Company is building a data center campus for Google on about 282 acres near Haggerty Road and I-94. The developer calls it an approximately 1 gigawatt facility. Because the land was already zoned for it, approval came through site plan review; the final site plan was approved in October 2026. The MPSC has approved DTE’s contracts with Google, and the Attorney General is seeking a rehearing.
| Owner / developer | Panattoni Development Company (PDC VBT, LLC)[13] |
|---|---|
| Operator / end user | Google LLC[14] |
| Site / address | East of Haggerty Rd, north of the I-94 Service Dr, west of Hannan Rd, south of I-275[13] |
| Parcel ID(s) | Section 13, T3S R8E; 38 tax parcels in Industrial Development District #27[15] |
| Acreage | ~282 acres; ~150 to be developed (developer)[13] |
| Power capacity | ~1 GW (developer)[7] |
| Water use | 2–3.6 million gal/day (developer estimate), bought from the Township[7] |
| Electric utility | DTE Electric — MPSC Case U-22058[11] |
| Stated investment | Developer: computer equipment “~$2B+”, real property “~$152M”[17] |
| Public money / incentives | 12-year real and personal Industrial Facilities Tax exemptions for Google (PA 198)[14] |
| Approval path | Site plan approval only: the land is zoned M-1, where data centers are a permitted use, so no rezoning or variance was needed[9] Public record |
| Google’s role | Township tax exemptions, MOU and MPSC contracts all name Google; Google’s own March 2026 post said only that it was “evaluating a site”[14] Public record |
| Non-disclosure agreement | The Township signed an NDA with Anchor Designs LLC in June 2025 barring disclosure that meetings had even taken place[16] Public record |
| Buildings | 6 buildings: ~973,000 sq ft footprint, ~1.42 million sq ft of floor area (final site plan review)[2] Public record |
| Developed area | About 150 of the 282 acres, with the rest left as open space[7] Developer / official claim |
| Water use | 2 to 3.6 million gallons a day, bought from the Township[7] Developer / official claim |
| Cooling and wastewater | 17 dual-cell cooling towers for Building 1; cooling-tower blowdown capped at 0.75 mgd, dry weather only, to the Township sewer; no groundwater wells[13] Public record |
| Backup generators | Developer says generators were “reduced by 85% from original design”; no count or rating is public[17] Developer / official claim |
| Jobs | About 1,500 construction jobs and 51+ permanent jobs[7] Developer / official claim |
| Contract terms | 20-year contract; 80% minimum billing demand; early termination payment of at least 15 years of minimums[11] Public record |
| New energy resources | Google pays for DTE to develop up to 1,600 MW of renewables and 480 MW of battery storage[11] Public record |
| Claimed customer benefit | $1.7 billion over 20 years, according to DTE[11] Developer / official claim |
| Cross-subsidy dispute | The Attorney General says the MPSC concedes other customers will subsidize the data center from 2035 to 2038[10] Developer / official claim |
| Local tax abatement | Real and personal Industrial Facilities Tax exemptions for Google, LLC: up to 36 months of construction plus 12 years[15] Public record |
| Wetlands | EGLE’s hearing described 13.55 acres of wetland impact and 573 feet of stream filled; press reports permits were approved in August 2026[23] Press report |
| Later Township limits | The Board deferred new applications for large industrial projects (Feb. 2026) and added hyperscale data centers (July 2026); the Township says Cannoli’s plan was locked in when submitted[3] Public record |
Panattoni Development Company is building a data center campus for Google on about 282 acres east of Haggerty Road and north of I-94 in Van Buren Township, Wayne County. The developer calls it an approximately 1 gigawatt facility. Until March 2026 it was known publicly only by its codename, Project Cannoli.
How it was approved
The land has been zoned M-1 Light Industrial since at least 2005, and the Township’s ordinance lists data centers as a permitted use there. That made this a site plan review rather than a rezoning, and the Township has said a moratorium would carry “significant potential for liability.” The Planning Commission approved the preliminary site plan in February 2026 and the final site plan in October. In May, the Board granted Google 12-year tax abatements and approved a development agreement setting conditions on water, sewer and cooling.
The MPSC conditionally approved DTE’s contracts to serve the site in October 2026. The Attorney General has asked for a rehearing.
Where it stands
Final site plan approval came on October 14, 2026, and press reports describe site work underway. DTE told the MPSC the facility would begin taking service in December 2027.
Numbers to treat with care
- Water. The 2 to 3.6 million gallons a day figure is the developer’s estimate. The development agreement caps cooling-tower discharge to the sewer, not water use.
- Generators. The developer says it cut generators by 85% from its original design, but no public record we have found gives a count or rating.
- Wetlands. The impact grew from about 10 acres in the Township’s January FAQ to 13.55 acres at EGLE’s June hearing. We have not yet linked the issued permit.
For a comparison, see our record of the Saline Township Stargate project.
Timeline
June 19, 2025
Township signs a non-disclosure agreement with Anchor Designs LLC[16]
December 16, 2025
Residents raise the project at the Board of Trustees[9]
The Township later answered that a moratorium carried “significant potential for liability.”
December 22, 2025
DTE preliminary service letter: “significant system upgrades will be required”[12]
February 11, 2026
Planning Commission approves the preliminary site plan, 5–2[25]
February 17, 2026
Board defers new applications for large industrial projects (Resolution 2026-02)[5]
Does not apply to Cannoli’s pending site plan.
March 17, 2026
Google identified as the company behind the project[18]
May 13, 2026
Planning Commission gives preliminary approval to the DTE/ITC switching station, 4–2[4]
May 19, 2026
Board grants tax exemptions to Google and approves the MOU and Development Agreement[14]
Creates Industrial Development District #27. 24 members of the public spoke.
June 16, 2026
EGLE online public hearing on the wetland permit application[23]
Hearing date per press (“Tuesday”); comments open to June 26.
July 21, 2026
Board extends the deferral and adds hyperscale data centers (Resolution 2026-18)[3]
October 1, 2026
MPSC conditionally approves DTE’s contracts with Google (Case U-22058)[11]
October 1, 2026
Wayne County Commission overrides the county executive’s veto of the tax break[22]
October 14, 2026
Planning Commission approves the final site plan, 5–1[21]
October 30, 2026
Attorney General petitions the MPSC for rehearing[10]
Records & resources
EGLE records & permits
- [1] EGLE MiEnviro site record, 82-10385 Haggerty Rd-Van Buren Twp Public site record linked from the Township FAQ.
Zoning, site plans & local approvals
- [2] Planning Commission packet, Oct. 14, 2026 — final site plan, Case 25-041 Applicant “PDC AK LPIC, LLC c/o Panattoni Development Company.” Final review: 6 buildings, 973,247 sq ft footprint; 1,423,112 sq ft gross floor area.
- [3] Board of Trustees minutes, July 21, 2026 — Resolution 2026-18 Extends the deferral and adds hyperscale data centers.
- [4] Planning Commission minutes, May 13, 2026 — DTE/ITC switching station, Case VBT-26-004 Preliminary approval 4–2 of a high-voltage substation/switching station within the Project Cannoli boundaries.
- [5] Board of Trustees minutes, Feb. 17, 2026 — Resolution 2026-02 Defers review of new applications for large industrial projects meeting certain criteria and power generation facilities.
- [6] Preliminary site plan review, Case VBT-25-041 (McKenna)
- [7] Van Buren Township Data Center FAQ (updated Jan. 12, 2026) Zoned M-1 Light Industrial “since at least 2005”; data centers a “Permitted Use.” Developer figures: ~1 GW, 2–3.6 million gal/day, ~1,500 construction and 51+ permanent jobs, 150 of 282 acres developed.
- [8] Van Buren Township — Data Center Project page The Township’s document hub for Project Cannoli.
- [9] Follow-up answers to residents’ questions from the Dec. 16, 2025 Board meeting “The application for Project Cannoli is a request for site plan approval not a rezoning.” On a moratorium: “Not without significant potential for liability.”
MPSC dockets & utility filings
- [10] Attorney General petitions for rehearing of the DTE–Google contracts Says the MPSC “concedes” other customers will subsidize the data center “at least for a four-year period from 2035 to 2038.”
- [11] MPSC approves DTE Electric–Google data center contracts, Case U-22058 20-year contract; 80% minimum billing demand; termination payment of at least 15 years of minimums; Google pays for up to 1,600 MW of renewables and 480 MW of storage. Service from Dec. 2027, maximum load by Dec. 2028.
- [12] DTE Electric preliminary service letter for Project Cannoli “Significant system upgrades will be required”; the letter “does not reserve load serving capacity.”
Contracts, incentives & agreements
- [13] Development Agreement, PDC VBT, LLC and Van Buren Township 282.2 acres optioned from Triple Creek Associates, LLC. Seventeen dual-cell cooling towers for Building 1; blowdown capped at 0.75 mgd, dry weather only. The posted copy’s signature pages are blank.
- [14] Board of Trustees minutes, May 19, 2026 Creates Industrial Development District #27; grants real and personal Industrial Facilities Tax exemptions to Google, LLC; approves an MOU with Google and the Development Agreement.
- [15] Board of Trustees packet, May 19, 2026 (IDD #27 and IFT resolutions) IFT for Google, LLC: up to 36-month construction period plus 12 years.
- [16] Mutual non-disclosure agreement, Anchor Designs LLC and Van Buren Township Bars disclosure of “the fact that a meeting or discussion has taken place between the parties.” Signed for Anchor Designs LLC on June 19, 2025.
Developer & official statements
- [17] Panattoni presentation to the Board of Trustees Developer figures: computer equipment “~$2B+”; real property “~$152M”; generators “reduced by 85% from original design.”
- [18] Van Buren Township press release on Google’s interest
- [19] Scaling clean energy and reliability in Michigan “Google is currently evaluating a site in Van Buren Township and will update the community as we know more.”
News coverage
- [20] Google wins zoning approval for huge data center near Detroit airport
- [21] Township vote paves way for Michigan’s second hyperscale data center Reports the 5–1 final site plan vote, and that EGLE approved wetland permits in August.
- [22] Wayne County overrides Evans veto of tax breaks for Van Buren data center
- [23] Google data center in Van Buren Township would destroy 13 acres of wetlands EGLE analyst at the online hearing: 13.55 acres of wetland impact, six culverts, 573 linear feet of stream filled. Comments open to June 26.
- [24] Google revealed as company behind hyperscale data center Project Cannoli
- [25] Planning Commission approves Project Cannoli preliminary site plan Reports a 5–2 vote.
- [26] Van Buren Township officials say proposed data center’s future likely out of their hands