Data Center Projects
Each data center project we track has its own page: a summary, its current status, the key facts, a dated timeline, and links to the public record behind each fact, including EGLE filings, land records, state incentive documents, and FOIA responses. Each fact links to its source.
Approved as of November 15, 2026
Google “Project Cannoli” Data Center — Van Buren Township
Van Buren Township, Wayne County
- Owner / developer
- Panattoni Development Company (PDC VBT, LLC)
- Power capacity
- ~1 GW (developer)
- Acreage
- ~282 acres; ~150 to be developed (developer)
Panattoni Development Company is building a data center campus for Google on about 282 acres near Haggerty Road and I-94. The developer calls it an approximately 1 gigawatt facility. Because the land was already zoned for it, approval came through site plan review; the final…
Under construction as of November 15, 2026
Oracle / OpenAI “Stargate” Data Center — Saline Township
Saline Township, Washtenaw County
- Owner / developer
- Related Digital (RD Michigan Property Owner I LLC)
- Power capacity
- 1,383 MW (MPSC order)
- Acreage
- ~575-acre site; ~250 acres developed
Related Digital is building a data center campus for Oracle and OpenAI’s Stargate program on about 575 acres along Michigan Avenue. The MPSC record describes it as a 1,383 MW facility. The Township denied the rezoning, was sued, and settled in an October 2025 consent…
Proposed as of November 15, 2026
University of Michigan / Los Alamos Research Computing Center — Textile Road
Ypsilanti Township, Washtenaw County
- Owner / developer
- University of Michigan (Board of Regents)
- Power capacity
- 50 MW at opening; 100 MW maximum planned
- Acreage
- 144 acres (U-M’s figure)
The University of Michigan and Los Alamos National Laboratory plan a high-performance computing center on about 144 acres along Textile Road, beside the Huron River. U-M says it would open at 50 MW and grow to a planned maximum of 100 MW, at a stated…
No projects match those filters.