Oracle / OpenAI “Stargate” Data Center — Saline Township
Under construction as of November 15, 2026[22] Saline Township, Washtenaw County
Related Digital is building a data center campus for Oracle and OpenAI’s Stargate program on about 575 acres along Michigan Avenue. The MPSC record describes it as a 1,383 MW facility. The Township denied the rezoning, was sued, and settled in an October 2025 consent judgment. Construction is underway, while appeals of the MPSC’s approval of DTE’s contracts are pending.
| Owner / developer | Related Digital (RD Michigan Property Owner I LLC)[5] |
|---|---|
| Operator / end user | Oracle (Green Chile Ventures LLC), for OpenAI’s Stargate[12] |
| Site / address | North side of Michigan Avenue (US-12), at the Bridgewater Township line[4] |
| Parcel ID(s) | Includes R-18-18300-002 and part of R-18-19-100-01[5] |
| Acreage | ~575-acre site; ~250 acres developed[4] |
| Power capacity | 1,383 MW (MPSC order)[12] |
| Water use | ~20,000 gal/day (developer estimate), from on-site wells; no high-water-use evaporative cooling[4] |
| Electric utility | DTE Electric — MPSC Case U-21990[12] |
| Stated investment | $4.81 billion in property listed in the tax abatement application; no figure from the companies[4] |
| Public money / incentives | Property tax abatement for up to 12 years (PA 198); sales and use tax exemption sought under MCL 205.54ee[5] |
| Ratepayer condition | MPSC approval is conditioned on the customer’s payments covering the full cost of serving it, so that other customers don’t pay[12] Public record |
| Contract terms | 19-year minimum term; 80% minimum billing demand; termination payment of up to 10 years of minimum billing[13] Public record |
| Battery storage | 1,383 MW of DTE-owned storage, paid for by the customer over 15 years; first 332 MW approved Mar. 27, 2026[9] Public record |
| Claimed customer benefit | About $300 million net benefit to other DTE customers[13] Developer / official claim |
| Buildings | Three single-story compute buildings of ~550,000 sq ft each, plus core, warehouse and administration buildings and two substations[5] Public record |
| Developed area | ~250 acres of the ~575-acre site; ~200 acres kept in agriculture; 47.5 acres under conservation easement[5] Public record |
| Cooling | No high-water-use evaporative cooling (consent judgment); the Township FAQ describes air-cooled equipment circulating a water/refrigerant mix[5] Public record |
| Backup generators | 14 diesel emergency generators and 1 diesel fire pump (air permit PTI0000135)[4] Public record |
| Noise limit | 55 dB at all property lines; generators run only for emergencies and testing, in daylight, no more than once a week[5] Public record |
| Payments to community | $14M total: $4M farmland preservation trust, $2M community investment fund, $8M to three fire departments[5] Public record |
| Decommissioning | Surety of $5–10 million; demolition required if vacant for 5 years[5] Public record |
| Jobs | More than 2,500 union construction jobs; more than 450 jobs on site; 1,500 county-wide[16] Developer / official claim |
| Wetlands | ~9.12 acres filled, 13.68 acres of mitigation in the River Raisin watershed[25] Press report |
| Wastewater | Draft NPDES permit MI0060445: ~20,000 gal/day of treated sanitary wastewater to the Saline River[1] Press report |
| Pending appeals | Attorney General and environmental groups are appealing the MPSC approval in the Court of Appeals[8] Public record |
Related Digital is building a data center campus for Oracle and OpenAI’s “Stargate” program on farmland along Michigan Avenue in Saline Township, Washtenaw County. In the Michigan Public Service Commission’s record it is a 1,383 MW facility.
How it was approved
The Township board denied the rezoning in September 2025. The developer and landowners sued two days later, arguing exclusionary zoning: the Township had no land zoned or planned for industrial use. The board voted to settle, and a consent judgment entered on October 15, 2025 rezoned the land and approved the site plan with conditions, including a 55 dB noise limit, no high-water-use evaporative cooling, farmland and conservation set-asides, $14 million in community payments, and a decommissioning surety.
The MPSC approved DTE’s contracts to serve the site in December 2025, without a contested case, on the condition that the customer’s payments cover the full cost of serving it. The Attorney General and environmental groups are appealing that approval.
Where it stands
Construction is underway. DTE told the MPSC that the facility’s electric load would begin to arrive in January 2027 and reach its maximum by December 2027.
Numbers to treat with care
- Cost. The companies have not published a figure. The tax abatement application lists $1.311 billion in real property and $3.5 billion in personal property. Press figures range from $7 billion to more than $43 billion; we have not found a primary source for those.
- Water. The ~20,000 gallons a day figure is the developer’s estimate, not a permit limit.
- Jobs. The companies’ release counts “more than 450 jobs onsite” and “1,500 jobs county-wide” in its text, and “2,000 permanent jobs county-wide” in its subheadline. None of these figures appears in any binding document we have found.
For what Saline’s experience means for other Michigan communities, see Data center siting.
Timeline
July 10, 2025
Conditional rezoning application filed (A-1 agricultural to I-1 industrial)[5]
August 14, 2025
Final site plan submitted[5]
September 10, 2025
Township board denies the rezoning, 4–1[5]
September 12, 2025
Developer and landowners sue the Township[6]
Exclusionary-zoning claim; Washtenaw County Circuit Court No. 2025-001577-CZ.
October 1, 2025
Township board votes 4–1 to settle[27]
October 15, 2025
Consent judgment entered[5]
Rezones the site and constitutes final site plan approval.
October 30, 2025
OpenAI, Oracle and Related Digital announce the Stargate site[16]
November 3, 2025
DTE files for approval of special contracts (MPSC Case U-21990)[12]
December 3, 2025
MPSC public hearing[15]
December 18, 2025
MPSC conditionally approves DTE’s contracts[12]
Approved ex parte, without a contested case.
January 8, 2026
Attorney General petitions for rehearing[11]
January 13, 2026
EGLE issues air permit PTI0000135[25]
January 15, 2026
DTE files its acceptance of the MPSC conditions[10]
January 16, 2026
EGLE issues wetland permit[25]
February 20, 2026
Circuit court denies a resident’s motion to intervene and undo the settlement[26]
March 27, 2026
MPSC denies rehearing and approves the first 332 MW of battery storage[9]
April 25, 2026
Financing secured; developer says major construction is underway[24]
April 28, 2026
Court of Appeals dismisses the resident’s appeal[29]
Without prejudice to a late appeal.
June 1, 2026
Construction launch ceremony with Gov. Whitmer[23]
August 6, 2026
Attorney General files Court of Appeals brief against the MPSC approval[8]
August 24, 2026
Comment period closes on draft wastewater permit MI0060445[1]
November 11, 2026
Township ratifies the industrial development district and reaffirms the tax abatement[20]
Records & resources
EGLE records & permits
- [1] River Raisin Watershed Council comments on draft NPDES permit MI0060445 Draft permit for ~20,000 gal/day of treated sanitary wastewater to the Saline River. Final decision not yet confirmed.
- [2] EGLE air Permit to Install PTI0000135 — 14 diesel emergency generators and 1 diesel fire pump Permit number and equipment per the Township FAQ; issue date per Planet Detroit (Feb. 24, 2026). Permit document not yet linked here.
Zoning, site plans & local approvals
- [3] Groundwater monitoring reports through Oct. 21, 2026 Notes artesian well conditions at monitoring wells MW-1, MW-1S and MW-2.
- [4] Saline Township Data Center FAQ (updated Jan. 28, 2026) Site: 8 properties, ~575 acres, north side of Michigan Ave. Developer water estimate ~20,000 gal/day. Air permit PTI0000135. IFEC application: $1.311B real + $3.5B personal property.
- [5] Consent judgment, RD Michigan Property Owner I LLC et al. v. Saline Township (No. 2025-001577-CZ) Rezones the site I-1 and constitutes final site plan approval. Sets conditions: no high-water-use evaporative cooling, 55 dB at property lines, ~200 acres kept in agriculture, 47.5 acres under conservation easement, $14M in payments, $5–10M decommissioning surety.
- [6] Complaint, RD Michigan Property Owner I LLC et al. v. Saline Township Exclusionary-zoning suit filed two days after the rezoning denial.
- [7] Saline Township — Data Center Update page The Township’s document hub: lawsuit documents, site plan, advisory committee, water-well information.
MPSC dockets & utility filings
- [8] Attorney General Court of Appeals brief (COA Nos. 380362, 380364, 380878) Consolidated with appeals by MEC/NRDC/Sierra Club (No. 380334) and GLREA (No. 380462). No decision as of Nov. 15, 2026.
- [9] MPSC denies rehearing and approves the first 332 MW of data-center battery storage Fish Creek (132 MW), Cold Creek (100 MW), Pine River (100 MW): “the first 332 MW of 1,383 MW of company-owned energy storage.”
- [10] DTE Electric acceptance letter, Case U-21990
- [11] Attorney General petition for rehearing, Case U-21990
- [12] MPSC order conditionally approving DTE’s special contracts, Case U-21990 “a 1.383 gigawatt (GW) data center facility … in Saline Township.” Customer: Green Chile Ventures LLC, an Oracle subsidiary. Load begins January 2027; contract runs to Feb. 28, 2045.
- [13] MPSC approves DTE Electric energy contracts for data center 19-year minimum term; 80% minimum billing demand; termination payment up to 10 years; 1,383 MW of storage paid for by the customer over 15 years.
- [14] MPSC e-docket, Case U-21990 (DTE Electric special contracts)
Meetings: agendas, minutes & video
Developer & official statements
- [16] OpenAI, Oracle and Related Digital announce Stargate data center site in Michigan Claims: “more than a gigawatt”; 250 acres; three 550,000 sq ft buildings; “more than 2,500 union construction jobs” and “more than 450 jobs onsite”; closed-loop cooling.
- [17] Related Digital Q&A on the data center proposal (posted by the Township) Pre-lawsuit proposal: development on “fewer than 250 acres”; 12 generators; 65 dB at property lines; ~20,000 gallons a day.
- [18] Related Digital well summary for EGLE (posted by the Township) Five temporary construction wells (384 GPM projected) and four permanent wells; “~20,000 gallons per day during permanent operations.”
News coverage
- [19] Companies behind Saline Township data center donate $500,000 to Clinton Fire Department Reports Saline will receive $7.5 million; the consent judgment specifies $7 million.
- [20] Saline Township sticks with Oracle tax break Board unanimously ratifies the industrial development district and reaffirms the “12-year, 50% tax break.”
- [21] Saline wants answers from EGLE on proposed data center wastewater permit
- [22] Construction progress at the Related Digital data center in Saline Township
- [23] Oracle and OpenAI start construction on Stargate data center campus in Saline Township
- [24] Saline Township data center: major construction underway, financing secured
- [25] Planet Detroit on the air and wetland permits Air permit issued Jan. 13, 2026 (projected NOx 34.86 tons/yr); wetland permit issued Jan. 16, 2026 (~9.12 acres filled, 13.68 acres mitigated).
- [26] Lawsuit aimed at stopping Saline Township data center rejected by Washtenaw County judge
- [27] Saline Township resident seeks to undo data center settlement Reports the Oct. 1, 2025 4–1 vote to settle.
- [28] Data center settlement earmarks millions for Saline Township
Other
- [29] Court of Appeals order dismissing the resident’s appeal (No. 380388) Dismissed for lack of jurisdiction, without prejudice to a late appeal; confirms the Oct. 15, 2025 consent judgment was the final judgment.
- [30] Data Center Zoning Considerations (Michigan Townships Association conference handout) Presents Saline as “The Cautionary Tale of Saline Township.”
- [31] Data center siting: why they end up near homes, and where they belong Our explainer, including the lesson of Saline Township.
This entry has not yet been fully verified against its sources. Spot an error or have a record we’re missing? Please tell us.