    • What Is a Data Center?
    • Project Timeline
    • Who’s Who
    • What They Said, and What the Record Shows
    • How Loud Is a Data Center?
    • How Much Water Does a Data Center Use?
    • Why We Oppose This Project
    • Why the Township Can’t Zone This — and Won’t Tax It
    • Responsible Opposition
    • The Nuclear Question
    • In the News
    • Sources & Links
  • Community Toolkit
    • Data Center Database
  • Take Action
    • Legislation
      • Bills We are Tracking
      • Contact Your Representatives
    • Sign Up for Updates
    • Contact Your Representatives
    • Our FOIA Guide Has Moved — and Grown
    • FOIA Center
    • Request a Yard Sign
    • Events
    • How to Use Your Ninety Seconds
    • Volunteer
  • Policies
    • Terms & Acceptable Use
    • Privacy Policy
  • News
  • Home
  • Resources
    • About YpsiDatacenter.org
    • What Is a Data Center?
    • Project Timeline
    • Who’s Who
    • What They Said, and What the Record Shows
    • How Loud Is a Data Center?
    • How Much Water Does a Data Center Use?
    • Why We Oppose This Project
    • Why the Township Can’t Zone This — and Won’t Tax It
    • Responsible Opposition
    • The Nuclear Question
    • In the News
    • Sources & Links
  • Community Toolkit
    • Data Center Database
  • Take Action
    • Legislation
      • Bills We are Tracking
      • Contact Your Representatives
    • Sign Up for Updates
    • Contact Your Representatives
    • Our FOIA Guide Has Moved — and Grown
    • FOIA Center
    • Request a Yard Sign
    • Events
    • How to Use Your Ninety Seconds
    • Volunteer
  • Policies
    • Terms & Acceptable Use
    • Privacy Policy
  • News
Close

Search

Subscribe

Google “Project Cannoli” Data Center — Van Buren Township

By Andy Melichar
November 15, 2026 2 Min Read
Comments Off on Google “Project Cannoli” Data Center — Van Buren Township

Approved as of November 15, 2026[20] Van Buren Township, Wayne County

Panattoni Development Company is building a data center campus for Google on about 282 acres near Haggerty Road and I-94. The developer calls it an approximately 1 gigawatt facility. Because the land was already zoned for it, approval came through site plan review; the final site plan was approved in October 2026. The MPSC has approved DTE’s contracts with Google, and the Attorney General is seeking a rehearing.

27 records ↓

Key facts
Owner / developerPanattoni Development Company (PDC VBT, LLC)[13]
Operator / end userGoogle LLC[14]
Site / addressEast of Haggerty Rd, north of the I-94 Service Dr, west of Hannan Rd, south of I-275[13]
Parcel ID(s)Section 13, T3S R8E; 38 tax parcels in Industrial Development District #27[15]
Acreage~282 acres; ~150 to be developed (developer)[13]
Power capacity~1 GW (developer)[7]
Water use2–3.6 million gal/day (developer estimate), bought from the Township[7]
Electric utilityDTE Electric — MPSC Case U-22058[11]
Stated investmentDeveloper: computer equipment “~$2B+”, real property “~$152M”[17]
Public money / incentives12-year real and personal Industrial Facilities Tax exemptions for Google (PA 198)[14]
Approval pathSite plan approval only: the land is zoned M-1, where data centers are a permitted use, so no rezoning or variance was needed[9] Public record
Google’s roleTownship tax exemptions, MOU and MPSC contracts all name Google; Google’s own March 2026 post said only that it was “evaluating a site”[14] Public record
Non-disclosure agreementThe Township signed an NDA with Anchor Designs LLC in June 2025 barring disclosure that meetings had even taken place[16] Public record
Buildings6 buildings: ~973,000 sq ft footprint, ~1.42 million sq ft of floor area (final site plan review)[2] Public record
Developed areaAbout 150 of the 282 acres, with the rest left as open space[7] Developer / official claim
Water use2 to 3.6 million gallons a day, bought from the Township[7] Developer / official claim
Cooling and wastewater17 dual-cell cooling towers for Building 1; cooling-tower blowdown capped at 0.75 mgd, dry weather only, to the Township sewer; no groundwater wells[13] Public record
Backup generatorsDeveloper says generators were “reduced by 85% from original design”; no count or rating is public[17] Developer / official claim
JobsAbout 1,500 construction jobs and 51+ permanent jobs[7] Developer / official claim
Contract terms20-year contract; 80% minimum billing demand; early termination payment of at least 15 years of minimums[11] Public record
New energy resourcesGoogle pays for DTE to develop up to 1,600 MW of renewables and 480 MW of battery storage[11] Public record
Claimed customer benefit$1.7 billion over 20 years, according to DTE[11] Developer / official claim
Cross-subsidy disputeThe Attorney General says the MPSC concedes other customers will subsidize the data center from 2035 to 2038[10] Developer / official claim
Local tax abatementReal and personal Industrial Facilities Tax exemptions for Google, LLC: up to 36 months of construction plus 12 years[15] Public record
WetlandsEGLE’s hearing described 13.55 acres of wetland impact and 573 feet of stream filled; press reports permits were approved in August 2026[23] Press report
Later Township limitsThe Board deferred new applications for large industrial projects (Feb. 2026) and added hyperscale data centers (July 2026); the Township says Cannoli’s plan was locked in when submitted[3] Public record

Panattoni Development Company is building a data center campus for Google on about 282 acres east of Haggerty Road and north of I-94 in Van Buren Township, Wayne County. The developer calls it an approximately 1 gigawatt facility. Until March 2026 it was known publicly only by its codename, Project Cannoli.

How it was approved

The land has been zoned M-1 Light Industrial since at least 2005, and the Township’s ordinance lists data centers as a permitted use there. That made this a site plan review rather than a rezoning, and the Township has said a moratorium would carry “significant potential for liability.” The Planning Commission approved the preliminary site plan in February 2026 and the final site plan in October. In May, the Board granted Google 12-year tax abatements and approved a development agreement setting conditions on water, sewer and cooling.

The MPSC conditionally approved DTE’s contracts to serve the site in October 2026. The Attorney General has asked for a rehearing.

Where it stands

Final site plan approval came on October 14, 2026, and press reports describe site work underway. DTE told the MPSC the facility would begin taking service in December 2027.

Numbers to treat with care

  • Water. The 2 to 3.6 million gallons a day figure is the developer’s estimate. The development agreement caps cooling-tower discharge to the sewer, not water use.
  • Generators. The developer says it cut generators by 85% from its original design, but no public record we have found gives a count or rating.
  • Wetlands. The impact grew from about 10 acres in the Township’s January FAQ to 13.55 acres at EGLE’s June hearing. We have not yet linked the issued permit.

For a comparison, see our record of the Saline Township Stargate project.

Timeline

  1. June 19, 2025

    Township signs a non-disclosure agreement with Anchor Designs LLC[16]

  2. December 16, 2025

    Residents raise the project at the Board of Trustees[9]

    The Township later answered that a moratorium carried “significant potential for liability.”

  3. December 22, 2025

    DTE preliminary service letter: “significant system upgrades will be required”[12]

  4. February 11, 2026

    Planning Commission approves the preliminary site plan, 5–2[25]

  5. February 17, 2026

    Board defers new applications for large industrial projects (Resolution 2026-02)[5]

    Does not apply to Cannoli’s pending site plan.

  6. March 17, 2026

    Google identified as the company behind the project[18]

  7. May 13, 2026

    Planning Commission gives preliminary approval to the DTE/ITC switching station, 4–2[4]

  8. May 19, 2026

    Board grants tax exemptions to Google and approves the MOU and Development Agreement[14]

    Creates Industrial Development District #27. 24 members of the public spoke.

  9. June 16, 2026

    EGLE online public hearing on the wetland permit application[23]

    Hearing date per press (“Tuesday”); comments open to June 26.

  10. July 21, 2026

    Board extends the deferral and adds hyperscale data centers (Resolution 2026-18)[3]

  11. October 1, 2026

    MPSC conditionally approves DTE’s contracts with Google (Case U-22058)[11]

  12. October 1, 2026

    Wayne County Commission overrides the county executive’s veto of the tax break[22]

  13. October 14, 2026

    Planning Commission approves the final site plan, 5–1[21]

  14. October 30, 2026

    Attorney General petitions the MPSC for rehearing[10]

Records & resources

EGLE records & permits

  1. [1] EGLE MiEnviro site record, 82-10385 Haggerty Rd-Van Buren Twp EGLEPublic site record linked from the Township FAQ.

Zoning, site plans & local approvals

  1. [2] Planning Commission packet, Oct. 14, 2026 — final site plan, Case 25-041 Van Buren Township Planning Commission · October 14, 2026Applicant “PDC AK LPIC, LLC c/o Panattoni Development Company.” Final review: 6 buildings, 973,247 sq ft footprint; 1,423,112 sq ft gross floor area.
  2. [3] Board of Trustees minutes, July 21, 2026 — Resolution 2026-18 Van Buren Township Board of Trustees · July 21, 2026Extends the deferral and adds hyperscale data centers.
  3. [4] Planning Commission minutes, May 13, 2026 — DTE/ITC switching station, Case VBT-26-004 Van Buren Township Planning Commission · May 13, 2026Preliminary approval 4–2 of a high-voltage substation/switching station within the Project Cannoli boundaries.
  4. [5] Board of Trustees minutes, Feb. 17, 2026 — Resolution 2026-02 Van Buren Township Board of Trustees · February 17, 2026Defers review of new applications for large industrial projects meeting certain criteria and power generation facilities.
  5. [6] Preliminary site plan review, Case VBT-25-041 (McKenna) McKenna, for Van Buren Township · February 3, 2026
  6. [7] Van Buren Township Data Center FAQ (updated Jan. 12, 2026) Charter Township of Van Buren · January 12, 2026Zoned M-1 Light Industrial “since at least 2005”; data centers a “Permitted Use.” Developer figures: ~1 GW, 2–3.6 million gal/day, ~1,500 construction and 51+ permanent jobs, 150 of 282 acres developed.
  7. [8] Van Buren Township — Data Center Project page Charter Township of Van BurenThe Township’s document hub for Project Cannoli.
  8. [9] Follow-up answers to residents’ questions from the Dec. 16, 2025 Board meeting Charter Township of Van Buren“The application for Project Cannoli is a request for site plan approval not a rezoning.” On a moratorium: “Not without significant potential for liability.”

MPSC dockets & utility filings

  1. [10] Attorney General petitions for rehearing of the DTE–Google contracts Michigan Attorney General · October 30, 2026Says the MPSC “concedes” other customers will subsidize the data center “at least for a four-year period from 2035 to 2038.”
  2. [11] MPSC approves DTE Electric–Google data center contracts, Case U-22058 Michigan Public Service Commission · October 1, 202620-year contract; 80% minimum billing demand; termination payment of at least 15 years of minimums; Google pays for up to 1,600 MW of renewables and 480 MW of storage. Service from Dec. 2027, maximum load by Dec. 2028.
  3. [12] DTE Electric preliminary service letter for Project Cannoli DTE Electric · December 22, 2025“Significant system upgrades will be required”; the letter “does not reserve load serving capacity.”

Contracts, incentives & agreements

  1. [13] Development Agreement, PDC VBT, LLC and Van Buren Township Charter Township of Van Buren · May 19, 2026282.2 acres optioned from Triple Creek Associates, LLC. Seventeen dual-cell cooling towers for Building 1; blowdown capped at 0.75 mgd, dry weather only. The posted copy’s signature pages are blank.
  2. [14] Board of Trustees minutes, May 19, 2026 Van Buren Township Board of Trustees · May 19, 2026Creates Industrial Development District #27; grants real and personal Industrial Facilities Tax exemptions to Google, LLC; approves an MOU with Google and the Development Agreement.
  3. [15] Board of Trustees packet, May 19, 2026 (IDD #27 and IFT resolutions) Van Buren Township Board of Trustees · May 19, 2026IFT for Google, LLC: up to 36-month construction period plus 12 years.
  4. [16] Mutual non-disclosure agreement, Anchor Designs LLC and Van Buren Township Charter Township of Van Buren · June 19, 2025Bars disclosure of “the fact that a meeting or discussion has taken place between the parties.” Signed for Anchor Designs LLC on June 19, 2025.

Developer & official statements

  1. [17] Panattoni presentation to the Board of Trustees Panattoni Development Company · May 19, 2026Developer figures: computer equipment “~$2B+”; real property “~$152M”; generators “reduced by 85% from original design.”
  2. [18] Van Buren Township press release on Google’s interest Charter Township of Van Buren · March 17, 2026
  3. [19] Scaling clean energy and reliability in Michigan Google · March 17, 2026“Google is currently evaluating a site in Van Buren Township and will update the community as we know more.”

News coverage

  1. [20] Google wins zoning approval for huge data center near Detroit airport Michigan Public · October 15, 2026
  2. [21] Township vote paves way for Michigan’s second hyperscale data center Bridge Michigan · October 14, 2026Reports the 5–1 final site plan vote, and that EGLE approved wetland permits in August.
  3. [22] Wayne County overrides Evans veto of tax breaks for Van Buren data center Fox 2 Detroit · October 1, 2026
  4. [23] Google data center in Van Buren Township would destroy 13 acres of wetlands Michigan Advance (from Planet Detroit) · June 18, 2026EGLE analyst at the online hearing: 13.55 acres of wetland impact, six culverts, 573 linear feet of stream filled. Comments open to June 26.
  5. [24] Google revealed as company behind hyperscale data center Project Cannoli Michigan Public · March 18, 2026
  6. [25] Planning Commission approves Project Cannoli preliminary site plan Planet Detroit · February 12, 2026Reports a 5–2 vote.
  7. [26] Van Buren Township officials say proposed data center’s future likely out of their hands WEMU · December 17, 2025

Other

  1. [27] Our record: Oracle / OpenAI “Stargate” data center, Saline Township YpsiDatacenter.org

This entry has not yet been fully verified against its sources. Spot an error or have a record we’re missing? Please tell us.

Author

Andy Melichar

This site is written and maintained by Andrew Melichar, a resident of Ypsilanti Township who lives near the Textile Road site. He has spent roughly thirty years in technology and currently leads a team of site reliability engineers responsible for datacenter infrastructure in facilities around the United States. He is not opposed to datacenters. He is opposed to this one, in this location, decided this way.

Follow Me
Other Articles
Previous

Oracle / OpenAI “Stargate” Data Center — Saline Township

Start Here
What is a Data Center?
Just the Facts
Project Links
Who's Who

Recent Posts

  • The Letter That Spoke for Ypsilanti Township
  • Not Yet: What the Regents Are Being Asked to Approve Thursday
  • “LANL Has Made No Commitment of Funds”
  • Four Years of Regents Minutes
  • How the Words Changed

Archives

  • November 2026
  • October 2026
  • September 2026
  • August 2026

Categories

  • Documents & Records
  • Legislation & Advocacy
  • Public Meetings
  • Responses
  • Uncategorized

Privacy Policy • Terms & Acceptable Use