Environmental Concerns with Data Centers and Battery Sites
The short version
Most of a data center’s environmental footprint comes from three things: the electricity it uses, the heat it has to get rid of, and the backup power it keeps ready. Those lead to the concerns neighbors raise most often — generator exhaust, constant noise, water use, stormwater, light and pressure on the power grid. Battery storage sites add a fire risk of their own.
None of these is automatic. A well-designed, well-sited, well-regulated project can manage most of them. The point of this page is to help you know what to ask about — and which agency is responsible for each answer.
Air: backup generators
Data centers keep large backup generators ready in case the grid fails — usually diesel, sometimes natural gas. A big campus can have dozens or even hundreds of them. Their exhaust contains nitrogen oxides, fine particles and other pollutants.
Under federal rules, generators classified as “emergency” engines may run up to 100 hours a year each for maintenance and testing, with no limit during a real emergency.1 One hundred hours sounds small, but across many generators tested on the same schedule, it adds up — and testing usually happens during the day, near whoever lives closest.
Large generator installations typically need an air permit from the state environmental agency. For scale: Michigan’s records for the Switch data center campus near Grand Rapids describe a permit covering sixty diesel emergency engines of 3,010 kilowatts each.2 Permit applications and inspection reports are public records, and many permits go out for public comment before they’re issued — another reason to sign up for your state agency’s notice alerts.
Noise
Data centers make noise from cooling equipment, rooftop fans, transformers and generator testing. The cooling and transformer noise is constant — day and night, every day — and often includes a low-frequency hum that carries farther and is harder to block than ordinary noise. Battery sites and substations hum too.
Noise is mostly a local issue, governed by your community’s zoning and noise ordinances. Ask for a noise study that predicts levels at the nearest homes, day and night, including low-frequency sound — not just at the edge of the developer’s property. See Environmental Noise.
Water
Some data centers cool with evaporating water, which can consume large amounts — especially in summer. Others use closed-loop or air cooling that uses much less. Nationally, data centers consumed an estimated 66 billion liters of water in 2023, most of it at the largest sites.3
Questions to ask include where the water comes from (a municipal system or private wells), how much will be used on the hottest day, and what happens to the wastewater. Cooling water that’s been recirculated can contain concentrated minerals and treatment chemicals. Some states attach conditions: Michigan’s data center tax exemption, for example, requires qualifying facilities to use municipal water, which shifts some of these questions to the local water system’s capacity, and Minnesota’s 2025 data center law adds requirements for water permits for the largest users. For how the different cooling technologies compare on water, energy, noise and chemicals, see How Data Centers Stay Cool.
Land, stormwater and wetlands
Large buildings and parking areas replace soil and vegetation with roofs and pavement, so rain runs off faster and carries sediment and pollutants with it. Projects near rivers, floodplains or wetlands deserve particular attention. Work in wetlands, floodplains and streams generally needs permits from the state environmental agency and sometimes the U.S. Army Corps of Engineers, and construction that disturbs an acre or more needs a stormwater construction permit and erosion controls — often handled through the state or county.
Contaminated land
Data centers are often built on former industrial land, and some states encourage that — Michigan, for example, offers longer data center tax exemptions for brownfield sites. Reusing contaminated land can be good, but digging, grading and building on it can disturb what’s in the ground.
Many state cleanup laws protect a new owner from liability for contamination that was already there if they assess the property before or soon after buying it — but still require precautions to prevent exposure and avoid making it worse. Ask what contamination is known, where sampling was done, and what precautions will be used during construction. Assessments done for liability protection are often designed to show that a property is contaminated, not to map every problem on it, so large parts of a site may never have been tested. (In Michigan, these are Baseline Environmental Assessments under Part 201.)
Fuel and chemicals
Generators need fuel on site — often thousands of gallons per generator in attached or separate tanks. Ask how much fuel will be stored, how spills will be contained, and how the site is protected near wells and waterways. Transformers hold insulating oil, and cooling systems use refrigerants and water-treatment chemicals.
Light
Security lighting runs all night. Ask for shielded, downward-facing fixtures and a lighting plan showing light levels at neighboring properties.
Energy and the grid
A large data center can use as much electricity as a small city. Meeting that demand can mean new power plants, keeping older fossil-fuel plants running longer, and new transmission lines. It can also affect electric rates, depending on who pays for new infrastructure. These questions are decided largely at the state level, by the state utility commission and in utility rate cases, which residents can follow and often comment on. Several Great Lakes states have adopted special data center tariffs — see the state resource pages.
Battery storage sites
Battery sites share the noise, light and stormwater concerns above, and add the risk of lithium-ion fires, which can release toxic smoke and contaminated runoff and are very hard to extinguish. See What Is a Battery Energy Storage System? for the details and the questions to ask.
Who handles what
Knowing which agency is responsible tells you where to ask, where to comment, and where to file a request for records. The names differ by state, but the division of responsibility is similar almost everywhere:
| Concern | Usually handled by |
|---|---|
| Zoning, site plan, noise, lighting, setbacks | Your township, city, village or county |
| Generator air permits | The state environmental agency’s air program |
| Wetlands, floodplains, streams, stormwater discharge | The state environmental agency, and sometimes the U.S. Army Corps of Engineers |
| Contaminated land | The state environmental agency’s cleanup program |
| Soil erosion during construction | The state or county |
| Water and sewer capacity | Your local water and sewer authority |
| Power plants, transmission lines, large battery sites, utility rates | The state utility commission or siting board |
| Fire safety and emergency response | Your local fire department and fire code official |
Your state resource page names the specific agencies in your state.
Good first questions to ask
- How many backup generators, what fuel, and how often and at what time of day will they be tested? Has an air permit been applied for?
- What will the noise level be at the nearest homes, day and night, including low-frequency sound?
- How will the building be cooled, and how much water will it use on the hottest day? Where will wastewater go?
- Is the site contaminated? Where was it sampled, and what precautions will be taken during construction?
- How close is it to wetlands, floodplains, rivers or private wells?
- How much fuel will be stored, and how are spills contained?
- Which permits are needed from which agencies, and when will each be decided?
Example: what this looked like in Ypsilanti Township
All three Textile Road parcels are listed by Michigan’s environmental agency, EGLE, as Part 201 “facilities,” with arsenic, chromium, silver, mercury and other contaminants found in soil and lead in groundwater. The University’s Baseline Environmental Assessments sampled small corners of the land; most of the acreage, including the Huron River frontage, was never tested. See Baseline Environmental Assessments.
Sources
- “The cloud needs an air permit,” Power Engineering, on federal New Source Performance Standards Subpart IIII (40 CFR Part 60).
- Michigan EGLE Air Quality Division, Scheduled Activity Report, Switch data center (SRN P0709), August 3, 2022.
- Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report, summarized by DatacenterDynamics.